Technical specifications

Scope of works:

  • 1 four-lane motorway tunnel,
  • total tunnel length 1,100 m,
  • length of total section on our behalf approx. 4,800m

Construction method

  • 6 floating sinking elements with a total length of 720m
  • excavation pits for the open construction method up to 30m deep

Geology

  • Weser sands and Lauenburg strata

General data

Project
Weser crossing, motorway tunnel under the river Weser

Client
DEGES

Contractor
Wayss & Freytag Ingenieurbau AG, North and Central sections

Construction period
08/2023 - 08/2028

Net construction costs
€ 650 million

 

Utilisation
Infrastructure
Type
Motorway tunnel, four lanes
Length
1,100 m
Construction Method
immersed tunnel

Images: DEGES

Related Projects

Related Projects

Cross River Rail Project
Cross River Rail Project
Australia

The State of Queensland in Australia expects new urban development and economic opportunities from the Cross River Rail infrastructure project. Wayss & Freytag Ingenieurbau is involved in this ambitious infrastructure project.

Read more
Light Rail Line U81
Light Rail Line U81
Germany

Connection of the Düsseldorf main railway station with the airport, the Düsseldorf trade fair center and the Airport City business park, construction of an underground railway station at the airport terminal.

Read more
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Germany

Landsberger Straße Sewer System Rehabilitation, Section 2, Munich

Read more